$272M to correct defects, complete Ministry of Health head office by mid-year

$272M to correct defects, complete Ministry of Health head office by mid-year
Minister of Health Dr. Frank Anthony addressing the Mental Health and Well-Being conference (Photo: DPI/ November 8, 2021)

“It’s an APNU+AFC project and we are now trying to fix it and correct all of the defects that were there.

“Right now, we are on schedule based on the timeline,” Dr. Anthony added.

Chung’s was awarded the contract in 2017, to construct the Public Health Ministry’s head office building at Lot 1 Brickdam to the tune of $356.8 million. Works commenced on July 19, 2018, and the contractor was supposed to complete the project within a year.

However, in September 2020, despite receiving $308.4 million for advance payments and mobilisation expenses, as well as two extensions totalling 317 days, permanent works were 70 per cent completed at the site.

Additionally, the contractor submitted a repriced bill of quantities, demanding an additional sum of $513.3 million on August 3, 2020 – a mere day after the Government officially changed hands with the swearing-in of President Dr Irfaan Ali.

Among the breaches highlighted are the lengthy delay in the completion of the building, and the increase of the prices on the bill of quantities for variations to the contract.

 